Rapid City’s data center rules delayed again, now to January

Data center rendering

Rapid City SD – In July, Mayor Jason Salamun told the City Council that “no data center is worth our water” and said stringent data center regulations would come before the council in August.

They won’t return to the Planning Commission until Jan. 21, 2027.

On Thursday, the commission approved Community Development staff’s recommendation to continue Ordinance 6746 to its Jan. 21 meeting.

According to the city, staff wants time to make edits and revisions to the draft “based on community feedback received during the recently-completed survey comment period.”

It is the second time the commission has pushed the ordinance back.

How we got here

  • July 20: At a special budget meeting, the mayor says data center regulations will come to council in August.
  • Sept. 10: The ordinance gets its first Planning Commission hearing. After about 90 minutes of comment and debate, commissioners continue it to Nov. 5. Commissioner Haven Stuck calls the issue “extremely complex.”
  • Oct. 14 to Nov. 2: The city holds an open house and runs an online survey.
  • Nov. 5: The commission continues it again, to Jan. 21.

After Jan. 21, the ordinance still has to go through the Legal & Finance Committee and two readings at City Council. The city’s previously posted schedule had council’s second reading on Dec. 7.

What the survey said

Between 888 and 923 people answered each of the survey’s questions, depending on the question.

For every limit in the draft, a large majority said it was “not restrictive enough,” ranging from 61% on the sound study requirement to 90% on the 1,000-foot buffer for large-scale facilities. Overall, about 80% of answers said the draft was too loose.

  • Distance: 82% said data centers should be more than 3,000 feet from homes. The draft uses 500 feet for micro facilities and 1,000 feet for large-scale ones.
  • Zoning: 71% said micro data centers should be prohibited in Light Industrial zoning. For large-scale facilities, 85% said the same. In Heavy Industrial, 76% said large-scale facilities should be prohibited.
  • Water first: 54% ranked water as their top concern.

The survey was open to anyone, so it reflects who chose to respond, not the city as a whole.

In two files of written answers, totaling more than 80 pages, respondents repeatedly asked the city to prohibit data centers outright, to put the question to a public vote, or to pause development with a moratorium. Water came up again and again.

“I think it should be on a ballot measure,” one respondent wrote.

A moratorium is on the table, at least legally

During public comment Thursday, a speaker asked the city to impose a moratorium on data center development.

That’s within the city’s power. Senate Bill 135, the “Data Center Bill of Rights” signed this spring, explicitly bars the state from preempting city or county authority to regulate or ban data centers.

The Legislature rejected a statewide one-year moratorium this session, along with a separate bill that would have required a one-mile residential setback and a 45-decibel noise cap.

Which feedback?

When the ordinance was continued in September, city staff said they would hold roundtables with Elevate Rapid City, Dream Design International and Black Hills Energy.

One topic was whether large-scale data centers, which require a conditional use permit in the draft, should instead be allowed by right in Heavy Industrial zones. Industry speakers at that hearing argued the permit requirement would discourage investment.

The survey that followed pointed the other way. Most respondents wanted large-scale facilities prohibited in Heavy Industrial, not made easier to build.

The city has not said which provisions staff plans to change.

Meanwhile, Sequitor Edge

The one data center announced for Rapid City so far is Sequitor Edge’s planned facility at the Black Hills Industrial Center, unveiled in February at Elevate Rapid City.

The project has grown since it was announced.

In February, the company described a 30,000-square-foot building on 10 acres, starting at 2 megawatts and growing to as much as 10 megawatts at full build-out, with a one-time cooling fill of about 19,000 to 20,000 gallons. Sequitor said it expected to break ground by late summer 2026.

Materials handed out in October, reported by The Sentinel ahead of the city’s open house, put the first phase at about 14.5 megawatts, with a one-time water fill of 65,000 gallons plus about 110,000 gallons a year.

The timeline had shifted to moving forward by the end of 2026, with operations in the second quarter of 2028.

Sequitor Edge, February vs. October

  • Power, first phase: 2 megawatts (up to 10 at full build-out) → about 14.5 megawatts
  • Tier under the draft ordinance: micro, a permitted use → large-scale, requiring a conditional use permit and a 1,000-foot buffer
  • Water, one-time fill: about 19,000 to 20,000 gallons → 65,000 gallons
  • Water, ongoing: none stated beyond the fill → about 110,000 gallons a year
  • Timeline: break ground by late summer 2026 → move forward by end of 2026, operating in Q2 2028
  • Above SB 135’s 10-megawatt threshold: no → yes

At 14.5 megawatts, Sequitor’s first phase would no longer be a “micro” facility under the draft ordinance. It would be large-scale, the tier that requires a conditional use permit and a 1,000-foot residential buffer. That is the same tier industry speakers asked the city in September to allow by right in Heavy Industrial zones. It would also cross SB 135’s 10-megawatt threshold for the state’s ratepayer protections.

At the February announcement, the site was described as already zoned for the use, with building permits still required from the city. In May, The Sentinel reported that no city permits had been filed.

Elsewhere, voters weighed in

While Rapid City’s rules wait, voters elsewhere answered the question directly.

On Tuesday, data center measures appeared on ballots 41 times in 10 states, and the side favoring development won once, according to Scientific American’s analysis of Ballotpedia data.

In Wells, Maine, more than 80% of voters approved a 180-day moratorium. The lone exception was Harwood, N.D., where voters rejected extra review of industrial projects while a $3 billion data center is under construction nearby.

The issue crossed party lines. Democratic governors-elect in Texas, Georgia and Ohio campaigned on tighter data center rules, and Texas’ Republican governor, Greg Abbott, had already imposed a data center moratorium in his state.

South Dakota’s statewide ballot had no data center measures.

Questions still open

  • Will staff’s revisions make the ordinance stricter, as most survey respondents asked, or looser, as industry speakers asked in September?
  • Which provisions are being rewritten?
  • Has Sequitor Edge applied for or received building permits?
  • If the ordinance passes, would it apply to Sequitor Edge, or would the project be grandfathered under current zoning?
  • Is the Black Hills Industrial Center site zoned Light or Heavy Industrial, and which tier would Sequitor’s current plan fall under?
  • Has Sequitor’s plan changed again since October?
  • Will the city consider the moratorium residents have asked for while the rules are pending?

What’s next

The Planning Commission takes up Ordinance 6746 again at 7 a.m. Thursday, Jan. 21, 2027, in the City Council Meeting Room at City Hall, 300 Sixth St.


Sourcing

City of Rapid City press release on the Nov. 5 continuance; Nov. 5, 2026 Planning Commission agenda and packet, including the 26OA006 survey results summary and open-ended response files (Oct. 14 to Nov. 2, 2026); Sequitor Edge and Elevate Rapid City announcement materials (Feb. 11, 2026); Scientific American, “The data center boom was on Tuesday ballots 41 times. It won once”; CNN Business; Reuters; Ballotpedia, South Dakota 2026 ballot measures.

Previously in The Sentinel: “No Data Center is Worth Our Water” (July 28); Rapid City’s new data center rules go before the Planning Commission (Sept. 9); Planning Commission delays vote after fractured hearing (Sept. 11); South Dakota Got Ahead of This (May 14); City urges residents to attend data center open house (Oct. 13).