Rapid City SD – Before Rapid City’s Planning Commission voted down a six-month data center moratorium Wednesday, Nov. 25, commissioners pressed city staff on what the alternative would and wouldn’t do.
Staff said a data center that meets the interim rules would need only a building permit, with no public notice. They also said nothing in the rules limits how often a cooling system can be refilled.
The commission rejected the moratorium 6–3, then recommended the interim rules 8–1. The Sentinel reported the votes the same day. This is the fuller account, based on the meeting recording.
Both options came from Mayor Jason Salamun as two versions of Ordinance 6762. The recommendation now goes to the Legal & Finance Committee and then to the City Council, which makes the final decision. The commission’s vote is advisory.
The interim rules, known as Option 2, would remain in effect until the city adopts a fuller data center ordinance. That ordinance, Ordinance 6746, has been continued to the commission’s Jan. 21, 2027 meeting.
The votes
Six-month moratorium (Option 1) — failed 6–3, roll call
- Yes: Jeff Bailey, Eric Braun (chair), Eirik Heikes
- No: Kelly Arguello, Karen Bulman, Mike Quasny, Pat Roseland, Haven Stuck, Vince Vidal
Heikes made the motion and Vidal seconded it.
Interim regulations (Option 2) — passed 8–1, voice vote
Bulman moved to adopt Option 2 and Roseland seconded. On the voice vote, Braun said he was the lone no: “So 8 to one with me voting no.”
Braun was the only commissioner who voted for the moratorium and against the interim rules.
What Option 2 would do
Current Planning Manager Jessica Olson walked commissioners through both options.
Right now, under rules adopted a couple of years ago, data centers are allowed in Light Industrial and Heavy Industrial districts with a building permit and “will serve” letters from the electric and water utilities.
Option 2 keeps the building-permit process and adds limits:
- No hyperscale data centers. Facilities using more than 10,000 gallons of water a day, or 50 megawatts of power or more, would be prohibited.
- No evaporative cooling. Systems would have to be air-cooled, closed-loop or use another non-evaporative technology.
- A cap on how much water a closed-loop system can hold: 9.6 gallons per kilowatt. For a 10-megawatt facility, that’s 96,000 gallons. For a 49-megawatt facility, it’s about 470,400 gallons.
- Disclosure requirements. Operators must estimate water use and provide the cooling system’s makeup, maintenance schedule and disposal methods.
- Generators for emergencies only. Olson defined an emergency as a complete power outage or an infrastructure failure. A utility reducing how much power a facility can draw does not count. Generator testing must happen during daytime hours.
- A noise limit of 65 dBA at the property line.
- A 3,000-foot setback from any zoning district that allows homes as a principal use. That doesn’t include General Agriculture, or districts where homes are only an accessory use, such as caretaker housing in Light Industrial.
Olson said the city is also updating Title 13 so closed-loop cooling water can’t be discharged into the sewer. It would have to be hauled off-site for recycling.
The difference between the two options, Olson said, is what happens if the fuller ordinance stalls.
The moratorium would have expired after six months, and the city would have gone back to current code. Option 2 stays in place “if another ordinance is never adopted.”
City staff made no recommendation on either option.
Why the mayor brought two options
Salamun told commissioners he asked staff for interim options after the commission continued Ordinance 6746 to January at its Nov. 5 meeting. He said that delay “frustrated me.”
“In the interim, my concern was that someone would apply for a permit and there’s very little we could do,” he said.
He said he wrote Option 2 so that it would provide protections even “if it was the only ordinance that got through the city council.” Offering both options, he said, “was strategic.” If he had brought only a moratorium and it failed, “we’d have no protections in place.”
Salamun announced in September that he won’t seek reelection. He said that was part of why he preferred a six-month moratorium to a one-year one: “I’m not mayor in a year, and I can’t promise you that the next mayor is going to be as concerned about this issue as I am.”
He also warned developers: “If you’re a data center hoping to sneak in a permit before we pass these rules, please don’t.”
No pending applications, but a window remains
Olson said the city has “no current applications for any data centers.” She said a project isn’t considered vested until a building permit is actually issued, which happens only after every reviewer has signed off.
Community Development Director Vicki Fisher said the commission’s Nov. 5 decision to continue the ordinance to January created an “optics” problem. Roseland had voted against that continuance.
“He may have been correct in that we continued it too long,” Fisher said. “The optics was we kicked the can too far down the road and someone could walk in with a building permit. Not what happened, but that’s the optics of it.”
Fisher told commissioners, “I can guarantee you come January 21st at planning commission, you will have a more enhanced, detailed ordinance for review.” Olson said a draft should be released for public comment sometime in December.
What commissioners asked, and what staff said
Stuck asked the most detailed questions about the interim rules.
Public notice. Stuck asked what a data center meeting Option 2’s requirements would still need from the city. Fisher said it would need a building permit with stamped engineering and architectural plans that meet city standards. “There would be no public notice of that building permit,” she said.
Refills. Stuck said the rules cap how much water a system can hold at once but don’t limit how often it can be refilled. City Water Superintendent Eric Boyda said the city would schedule fills outside peak months like July and August. He said refills of systems maintained in sections would ideally stay under the 10,000-gallon daily limit. “But to directly answer your question, there wasn’t anything restricting the amount of those refills,” he said.
Enforcement. Staff said the city’s smart water meters show when a customer is using water. If a user goes over its committed amount, the city can shut off the water “until they come back into compliance.”
Water estimates. Stuck noted that applicants only estimate their water use, and actual use could later “substantially deviate” from that estimate.
Comparison to other users. Boyda said a large grocery store averages about 40,000 gallons of water a day, four times Option 2’s daily limit. He said he couldn’t speak to how much a slaughterhouse or battery plant would use, but that heavy industry “would use a substantial amount of water.”
Generator commissioning. Stuck said the rules limit when generators can be tested but appear to put “little or no limitation” on how long a new facility can stay in commissioning mode.
Fisher said a new generator has to run for a period under load to prove it works. She said the intent is that “the time of day that happens and the length of time it’s allowed is reviewed and approved.”
In-house server rooms. Stuck asked why the definition of a data center now excludes facilities “clearly incidental and subordinate to a permitted principal use.”
Fisher said the language responds to residents who pointed out that banks, the hospital, the city and even home gamers have server rooms. She said those rooms are allowed only as an accessory use, can’t stand alone, and can only be used by the business itself. They “cannot hold space for any and sell it to anyone else.”
How commissioners explained their votes
Heikes, who made the moratorium motion, said he was “leaning toward the moratorium” and was “hyper listening today.” Before Olson’s answer on applications, he asked: “Is somebody trying to sneak a big old fat permit through while this is being stalled?”
Heikes also said, “We’re in a drought.” In August, the city extended its watering restrictions to the entire year after Pactola Reservoir’s status moved from “concern” to “alert.” Boyda said at the time that the decision was based on low inflows into the reservoir, not on its water level.
Bulman made the Option 2 motion. “I think nobody in this community wants a data center,” she said, adding that most people picture the very large facilities they’ve seen on TV.
Option 2, she said, “says there will be no mega centers.” It “at least gives us something that’s there that’s better than what it is today.”
Roseland said he voted against the Nov. 5 continuance because “I don’t want to see this thing kicked down the road forever and ever and ever.” He said he worried a moratorium would end with the community “sitting here at the same time saying we don’t want data centers no matter what.” He compared data center water use to that of other large users, including Sanford Health’s planned hospital.
Arguello, who said he has worked in building and construction his whole career, called Option 2 a ban on large facilities. “50 megawatts is the max. That is a ban,” he said.
He noted the ordinance can be changed later. He compared data center water use to that of a ski area, golf courses and pools.
Quasny said commissioners read the public comments. “Whether there’s a data center or not, I think we got a water problem,” he said.
Vidal told the room that South Dakotans, “especially West River,” take water seriously. He pointed to the history of the Woonsocket artesian well. He said he still had questions he didn’t think had been answered.
Braun said he thought the public wanted the six-month pause “because they think that will stop everything for six months.” He said large data centers are something “nobody wants in the community.” His concern, he said, was “the rest of the ones that we have to deal with.”
Bailey did not speak on the item.
Hani Shafai’s 49-megawatt project
Dream Design International founder Hani Shafai described a facility of about 49 megawatts that he said could potentially be built in Rapid City. He estimated its economic impact at about $24.5 million. He said Dream Design had worked with four data center developers, including two hyperscalers he said the company turned away.
A 49-megawatt facility would fall under Option 2’s 50-megawatt cap.
Shafai said the facility’s initial closed-loop fill would be about 325,000 gallons, using a glycol compound mixed with water. He compared that with the lap pool at Roosevelt Park, which he put at about 375,000 gallons. He said the pool is effectively filled three times a season because of evaporation. Under Option 2’s storage cap, a 49-megawatt facility could hold up to about 470,400 gallons.
Asked by Quasny about the system’s life cycle, Shafai said the fluid is replaced about every 10 years in 20% sections. “Over 5 years, which is from year 10 to about the year 15, they take, replace the material and recycle it,” he said. He said the removed fluid is recycled and reused and is “not actually harmful to the environment.” He said other water use at the site would be for irrigation and employee restrooms.
Shafai also responded to the mayor’s warning about permits. “I promise you we would never sneak a building permit unless it meets all requirements,” he said.
The Sentinel has not independently verified Shafai’s water figures.
Public comment
At least 15 members of the public addressed the commission on the item. Nine supported the moratorium. Two opposed data centers outright without backing either option.
The four speakers who supported Option 2 came from two development groups: Shafai and Mike Stanley of Dream Design, and Garth Wadsworth and Jack Valentine of Elevate Rapid City.
Wadsworth said a moratorium could send projects to Meade County or Box Elder, where he said Rapid City’s rules wouldn’t reach. He noted that the Madison and Minnelusa aquifers “do not stop at the city boundary.” He said the commission had heard from people who don’t want data centers, but “you did not hear from all the other 80,000 residents.”
Valentine said Elevate “is not currently working with, representing, nor are we involved with any data center development projects.” He said a moratorium “sends the wrong message” to businesses and investors.
Stanley said Dream Design’s Black Hills Industrial Center has worked with several data center developers, none of which moved forward. He noted that Heavy Industrial zoning already allows uses such as chemical manufacturing and foundries by right.
Moratorium supporters raised environmental concerns, noise and trust.
One speaker who opposed data centers outright said regulations were needed but “we probably need to go a little further.” The same speaker said a friend had told them meadowlarks are affected by noise at 30 decibels, well below Option 2’s 65 dBA limit. Quasny later responded to that point: “I love my meadowlarks. I have a problem if my meadowlarks disappear because I like to have my morning coffee and listen to those meadowlarks.”
Another said 65 dBA is not strict enough.
Another told the commission, “I have a very, very low confidence in this body and the city council to listen to everyone here.”
Former council member Ron Sasso said he had drafted an ordinance to prohibit data centers and brought it to the City Council, but no council member moved to put it on the agenda. He said the city’s public survey did not offer a ban as an option. Fisher said the survey, which closed Nov. 2, drew more than 900 comments.
Another speaker said developers preferring Option 2 “should tell this council everything that they need to know.” That speaker asked whether a 49.9-megawatt proposal was designed to stay just under the 50-megawatt threshold.
What happens next
- Legal & Finance Committee: Wednesday, Dec. 2, 12:30 p.m., City Council Chambers
- City Council, first reading: Monday, Dec. 7, 6:30 p.m., City Council Chambers
- City Council, second reading: Monday, Dec. 21, 6:30 p.m., City Council Chambers
- Effective date: 20 days after the ordinance summary is published. Olson said the exact date will be set once publication happens.
- Fuller ordinance (6746): a draft is expected for public comment in December. It goes back to the Planning Commission on Jan. 21, 2027.
Salamun said he will sign whichever option the council passes.
Sourcing
Quotes and vote tallies come from the City of Rapid City’s video recording of the Nov. 25, 2026 Planning Commission meeting and its auto-generated transcript, reviewed against the recording. Quotes are lightly edited to remove filler words. Ordinance details come from the staff presentation. Water restriction details come from the City of Rapid City’s Aug. 20, 2026 news release. Calculations of the closed-loop storage cap are the Sentinel’s, using the 9.6-gallons-per-kilowatt figure in Option 2.